Pavement rehabilitation and select curb and gutter replacement of Emerson Ave, Sylvandale Rd, Sylvandale Court S, Sylvandale Court, Laura Street/Court, Ivy Falls Court, Maple Park Dr, and Ivy Hill Drive. Utility improvements include watermain replacement within the project area and select improvements to the storm sewer network for drainage improvements. Improvements to Ivy Hill Park include rehabilitation of the existing parking lot and improvements to the existing basketball court.

Project updates

Turf restoration project-wide remains a top priority for City staff and the contractor. The contractor treated for weeds late in the summer and has been continually adding topsoil and seed in areas with insufficient turf growth. Growth will be monitored and addressed as needed throughout the fall.

Emerson Avenue Weekly Updates

Current phase

Construction

Timeline

Utility and roadway improvements were completed in 2024. Turf restoration will continue to occur through the fall of 2025.

Additional resources & Updates

An Assessment Hearing was held at the City Council meeting on Wednesday, October 30th, 2024, at City Hall. Notifications were mailed to properties included on the proposed Assessment Roll.

Emerson Avenue 2025 Construction Notice

Emerson Avenue Construction Update

Emerson Ave Construction Notice

Emerson Ave Street Improvements Feasibility Report

Emerson Ave Informational Meeting Handout

PROJECT AREA

Project Area
  1. Ryan Ruzek

    Public Works Director/ City Engineer

  2. Lucas Ritchie

    Assistant City Engineer

  3. Engineering and Public Works