Victoria Curve and Orchard Hill Project
The City of Mendota Heights utilizes a multi-year pavement management plan to prioritize the infrastructure improvement needs within the city. Street improvement needs are summarized within the Street Improvement Plan (SIP). The Street Improvement Plan suggests improvements to Victoria Curve and Orchard Hill.
Mendota Heights Victoria Curve Feasibility Report (PDF)
Link to Project Updates
Preliminary Schedule:
Authorize Preparation of Feasibility Report | August 2022 |
Accept Feasibility Report | December 2022 |
Neighborhood Meeting | January 2023 |
Public Hearing/Order Improvements | January 2023 |
Accept Plans and Specifications and Authorize Bidding | March 2023 |
Award Contract | April 2023 |
Commencement of Construction | May/June 2023 |
Substantial Completion of Construction | September 2023 |
Assessment Hearing/Certify Assessments to County | October 2023 |
Warranty Inspection | June 2023 |