[ARCHIVED] Oct. 6 Infrastructure Projects Update

Construction Sign

Victoria Curve and Orchard Hill Street Improvements –Victoria Curve (from Highway 13 to Hunter Lane) and Orchard Hill were paved with the first lift of bituminous this week. The concrete contractor began installing curb on Friday before rain moved in and the work had to be delayed. The concrete work is expected to continue the week of October 9. Project updates are available at Mendotaheightsmn.gov/Projects.

Highway 62 – MnDOT completed the Highway 62 Concrete Repair Project and the Highway opened on October 5.  This project is now complete.